Skip to main content

Week 3

During week 3, the team built and tested the first two prototypes of the heat pipe. The construction of the heat pipes was straightforward as these two prototypes had very little complexity to them. A process of rapid prototyping was utilized to come up with two working devices that would be able to obtain useful data for quick design iterations. Below are two construction photos of the first heat pipe. The first image shows the interior mesh used as a wick and the bottom picture is the crimped pipe end before soldering.
A detailed construction log can be viewed on the Heat Pipe Fabrication page.

Testing
The testing involved using a clamp to hold the pipe in place while hot air was applied to one of the ends of the pipe. Two thermocouple probes were used to measure the change in temperature of the ends of the heat pipe over time. A picture of the apparatus used is shown below:

The results for the first prototype show that it was relatively inefficient, due to the fact that not much acetone fluid was inside the pipe. More fluid will be included in future prototypes to produce better results. Trial 1 was conducted in a horizontal orientation while Trial 2 was conducted at an angle. This was to examine if orientation had an effect on the efficiency. A table of the results in two trials is shown below:
Temperature 1 represents the evaporator end of the heat pipe and temperature 2 is the condenser end.

The results for the second prototype show that it was more efficient as more acetone was added to the inside of the pipe. The results for the second prototype are shown below:
Since a substantial improvement was observed with the second prototype, the team decided not to run a test in the angled orientation because the first test proved that heat pipe design and functionality was heading in the proper direction. 

Data Analysis:
Condensing the raw data into plots allows the function of the heat pipe to be visualized. Graphs 1 and 2 represent the three initial trial runs for the heat pipe prototypes.
Graph 1:

Graph 2:
The two graphs demonstrate the inefficiencies of the first two heat pipe prototypes but show increasing performance between the two. The first tests of prototype 1 show that over the course of 240 seconds there was only an increase of 10 degrees over two trials in the horizontal and angled orientations. Prototype 2 was capable of a temperature increase of 24 degrees over the same interval. Comparing the efficiencies of the two heat pipes, Prototype 2 had a 140% increase in performance over Prototype 1, a massive improvement. There was no change to the construction methods between Prototype 1 and 2 but acetone filling was altered on Prototype 2. The original method was to vaporize some of the acetone and then quickly seal off the end with solder. On the first attempt, an estimated 50-75% of the acetone was lost due to overheating which would severely hamper the heat pipe's ability to transfer heat. The filling and heating process on Prototype 2 was changed to limit this loss. The data proves that the new method works in practice.We were able to conduct all of our week 3 goals to expedite the heat pipe design and testing  allowing the team to narrow on the most effective heat pipe design with the highest performance that can be achieved.  

Comments

Popular posts from this blog

Week 5: Lab

The team conducted some more tests on Prototype 2 as it was the best performing heat pipe constructed thus far. The test was conducted in the angled orientation as Prototype 2 hadn't been tested in that configuration yet. The results were promising as Prototype 2 exceeded expectations and transferred heat effectively throughout the test. The condenser end increased by 52 degrees over 300 seconds which was an improvement over the horizontal test conducted with Prototype 2. In both tests, the difference between the condenser temperature and the evaporator temperature was calculated and displayed on the graphs. The graph below shows the first test for Prototype 2. To verify our results the test was run a second time but for a longer period of time in order to narrow down on where the heat pipe's maximum operating temperature would be. The results are shown below. For Prototype 2, the effective temperature limit of the heat pipe can be approximated to 125 F without a hea...

Week 1

The primary focus of week 1 was to research the existing designs of a heat pipe, understand the mechanisms at which they operate, and come up with ideas to build an efficient low temperature heat pipe. The main purpose of the heat pipe is to transfer heat from one place to another. Research was conducted on low-temperature applications and the advantage and disadvantage of different designs. After analyzing the information and taking into account the time and budget restriction for this project, an initial design of the heat pipe was generated.  The heat pipe will be made of copper tubing with mesh inside the tubes to serve as a wick. There will also be Aluminum heatsink fins at the condenser end to increase surface area for the spreading of heat to the surrounding. The main tasks include research, initial design, ordering of material, generation of CAD model, construction, testing, and optimization. The design and construction of the heat pipe are limited to a budget of $400 ...

Week 4: Lab

This week, prototype 3 and 4 were constructed and tested. As shown in the image below, the shorter one, prototype 4, has a length of 1 foot and the longer one, prototype 3, has a length of 2 feet. The effect of the length of the heat pipe on its efficiency is tested this week. Below is the tables and graphs of the testing done in lab this week. From the test results, it can be concluded that prototype 4 performed better than prototype 3. In 240 seconds, prototype 4 had a temperature increase of 12 degrees, while prototype 3 increased only 2 degrees. A possible reason is that the because the prototype 3 is longer in length, and so heat transfer takes longer. It is also possible due to heat loss along the length of the heat pipe.